Posted on June 30, 2017 at 4:29 PM by Melissa Myers
The City of Lebanon has the following projects scheduled for the week of July 3rd.
An electric crew is scheduled to set new poles on Ohio Street to connect to the solar farm.
Another Electric crew will be at Lowe Boats to install a new electric service.
The tree crew continues to trim limbs along Woodspice.
The inflow and infiltration crew is scheduled to video and clean sewer lines in the vicinity east of Highway 5 and south of East Bland Road to Mountrose Street.
The Catherine Street project continues as crews install new water and sewer lines between Sarah and Wood Street. Catherine Street is closed for construction and motorists must use alternate routes until this project is complete.
New sidewalk construction continues along Jefferson Avenue, between Second and Third Streets.
At the Agricultural Area near the Cowan Civic Center, excavation work is taking place for the Ag Barn expansion effort.
And a maintenance crew is scheduled to sweep and seal street cracks in various locations around Lebanon.
Motorists are asked use extra caution and watch for traffic control signs in these areas mentioned.
Street maintenance crews will perform the last round of storm debris pickup beginning July 3rd and end July 7th. Residential properties that still have storm debris are asked to stack it parallel to the curb in 10-12 foot lengths.
For additional information visit the City’s website, www.lebanonmissouri.org, or find us on Facebook