Weather permitting Lebanon’s Public Works Department has the following projects scheduled for the week of May 11, 2015.

Street construction crews are installing new sidewalk curb ramps at the intersections of Third and Monroe and at Third and Jackson. Excavation for sidewalk curb ramps is taking place at the intersection of Second and Madison.

Street maintenance crews will be patching potholes in various locations throughout the City.

Electric construction crews are installing conduit on East Fremont, while another crew works on Michigan Street replacing cross arms.

The tree crew is scheduled to work along Standwood Drive this week.

Weather permitting, the Inflow and Infiltration crew is scheduled to be in residential backyards around the Farmers Lane, King James and Orchard Hills areas. They are scheduled to clean and/or video sewer lines. In case of rain the Inflow and Infiltration crew is tentatively scheduled to work north of Elm Street and east of Highway 5, around the Harwood, Clark and Woodhill areas.
 
For additional information please visit the City’s website, lebanonmissouri.org, or find us on Facebook.

Contact:
Melissa G. Myers
Public Works Administration
(417) 532-2156 x1031
City of Lebanon
P.O. Box 111
Lebanon, MO 65536
www.lebanonmissouri.org